The construction of the new hospital in Barsana is progressing well.

The structure will be stilt, ground plus 2 floors, admeasuring about 56,000 sqft.

The foundation of the building has been finished. The concrete casting of the plinth and 50% beams are also completed. About 950 cubic meters of concrete and 100 mt of steel has been used till now.

The slab of the stilt floor is expected to be cast by the end of Sept’22.



Preparing tor steel structure before casting of concrete

Main entrance of the project site of the new hospital



Concreting of plinth beam in progress

Preparing tor steel structure before casting of concrete